Rapid UIO Project- Underground Non-metallic Piping Firewater Network Installation (16 Kilometre Pipeline)
Project : RAPID UIO PROJECT- UNDERGROUND NON-METALLIC PIPING
FIREWATER NETWORK INSTALLATION (16 KILOMETRE PIPELINE)
Main Contractor : BWS Engineering Sdn. Bhd.
Sub-Contractor : KPG Engineering Sdn. Bhd.
Contract Value : RM 70,000,000.00
Duration : Jan 2018 to Nov 2019
Location : Pengerang, Johor
Scope of Work : Project Work Inclusive of
Civil Work Package :
– Excavation
– Backfill
– Box Culvert Installation
Piping Work
– GRE Pipe Laying
– GRE Lamination Work
– Hydrotest